1. Define the base pipe

The coating description does not replace the steel pipe specification.

  • Provide steel grade, pipe standard, outside diameter and wall thickness.
  • State length, quantity and welded/seamless construction requirements.
  • Describe the conveyed medium, design conditions and installation environment.

2. Define inside and outside protection

Treat internal lining and external coating as separate requirements. A colour or photograph alone does not identify a coating system.

  • State the coating system required by the project, such as the specified TPEP arrangement.
  • Provide the layer specification and required coating thickness.
  • Include end cutbacks, field-joint treatment and handling requirements.

3. Agree acceptance and packing

Set the inspection scope before ordering so it can be included in the quotation.

  • List required thickness, adhesion or holiday detection checks where applicable.
  • Specify the acceptance standard and required inspection records.
  • Confirm supports, lifting protection, end caps and delivery destination.